Discussions New post

Discuss with the community about issues, best practices or project management.

Grey out completed tasks from the Resource Load Chart


Comments 3

  • Avatar
    Rashmi Likhite

    You can already filter out completed tasks from RLC. Simply Edit the report, add a filter to include T:% Complete and check 'prompt'. The user running the report can then have the choice to filter out tasks that are 100% complete. 

    0
    Comment actions Permalink
  • Avatar
    Matthew Wan

    Thanks, was using the schedule status which is bugged and shows nothing if selected as filter

    0
    Comment actions Permalink
  • Avatar
    Hassan El-Hadidy
    Also, when you edit the report, add a filter to include T:Status and check "Incomplete". Then run the resource load report.
    0
    Comment actions Permalink

Please sign in to leave a comment.