    Rashmi Likhite

    You can already filter out completed tasks from RLC. Simply Edit the report, add a filter to include T:% Complete and check 'prompt'. The user running the report can then have the choice to filter out tasks that are 100% complete. 

  • Avatar
    Matthew Wan

    Thanks, was using the schedule status which is bugged and shows nothing if selected as filter

  • Avatar
    Hassan El-Hadidy
    Also, when you edit the report, add a filter to include T:Status and check "Incomplete". Then run the resource load report.