Importing Excel Task CSV


Comments 1

  • Avatar
    Rashmi Likhite

    Celoxis calculates some fields automatically like the duration - depending on the Start and Finish date, Work(h) depending on resource allocation. Hence, we do not import these columns. Also, as CSV is a flat list file (i.e without parent-child hierarchy), the fields that rollup to parent tasks cannot be imported.