Is it possible to link Task state into certain % of completion (Automatically)


Comments 2

  • Avatar
    Lisa Dancewicz

    This is actually a very relevant request.

    In many cases, we too have multiple resources assigned to one task. Where one resource may have completed their component, the other may only complete 10%.

    Is there possibility of formulating so that the total % complete takes into consideration the two various stages of completion based on the resources assigned to the one task?

     

  • Avatar
    Beena W

    @Lisa -- For every project, you can pick the "Task % Complete method" of your choice.  Edit your project and select the Default Task % Complete method as "Weighted Average of % entered by each resource".