Can I prepare a project plan with some placeholder resources?


Comments 1

  • Avatar
    Celoxis Support

    Celoxis has a concept of 'Generic Resources'.  You can define any number of such Generic Resources (which are basically users without a login/pwd - so not counted towards a license). 
    So for example you can create a user called 'Developer', 'Tester', 'Senior Developer' and so on. 

    Then go ahead and plan your project and assign tasks to these 'generic resources'.  Once you are ready to progress and have actual resources finalized, simply go to the Resource Load Chart for that project. Against the tasks which have the generic resources attached, simply click on the 'Allocation' and reallocate the efforts to the named resource. 