The project's percent complete is calculated as...
If 'p' is the percentage complete of a task and 'w 'is the estimated efforts on a project, then:
Percent complete of a project = (w1 × p1 + w2 × p2+...) ÷ (w1 + w2+...) where 1 and 2 are its tasks.
Some of your tasks must be 100%complete,some 0%complete and some % complete. So the %complete for project shows accordingly.