Different cost rate for same user according to project


Comments 1

  • Avatar
    Rashmi Likhite

    Yes, it is possible to have users with different cost rate per project. If you have defined a cost rate for a project for a user and one at company level, then the one defined at project level is applied for calculating cost. If nothing is specified for at project level, then the one at company level is applied for calculating cost.

    For adding user cost rate per project follow the steps below :

    • Open the project, under 'More Actions', click on 'User Cost Rates'.
    • Select the user and enter the associated information and click 'Add'.

    If you still have any doubts, please open a support ticket and we will assist you further.

     