    Hi Dorte, 

    It is not possible to have a resource assigned to multiple work calendars in Celoxis. However I'd suggest creating Work Exceptions (Events) for the specific resource and choose the Impacts Scheduling drop down as 'Yes, Non-Working'.  So in your case, you can have the resource assigned to the 'Default' calendar and create the following events -

    1)  Week 1 - No Event, i.e. normal work calendar hours.

    2) Week 2 - Create an event with Impacts Scheduling option selected as 'Yes, Non-Working' for 6 hours and set the end date under 'Repeat' Tab

    and so on.

    Hope this helps!