Discussions New post

Discuss with the community about issues, best practices or project management.

Automatic change sheduled start date (when previous finish before or later)


Comments 2

  • Avatar
    Kaustubh Mahabal

    Yes, it is possible to automatically move start date of a successor task earlier (or later) than planned start date if a predecessor task finishes earlier (or later).

    • To apply this, Edit Project --> Go to "Options" tab --> Enable "Tasks should start when all predecessors are complete" option.
    0
    Comment actions Permalink
  • Avatar
    Marco Andreolli

    Thanks, this is what I need!

    0
    Comment actions Permalink

Please sign in to leave a comment.