Hours-based resource allocation is now available as a Beta feature.
This company-wide scheduling option allows you to allocate resources to tasks by specifying the number of hours each resource is expected to contribute, instead of using percentage-based allocation.
To enable this feature, navigate to:
Admin > Project > Project Options
and enable “Allocate task resources in hours (BETA)”.
Once enabled:
- Resource allocations across projects will be managed in hours.
- Existing percentage-based allocations will be automatically converted to hours.
- The setting applies company-wide, so resource allocation will use either hours or percentages across all projects.
Comments